323b dong invested in seafood processing plant

22-Nov-2011 Intellasia | Thoi Bao Kinh Te Vietnam page 3 | 3:01 PM Print This Post

Huy Thuan Seafood Processing Joint Stock Co announced to start construction works on a new shrimp processing plant for export in Giao Long Industrial Park on November 20, 2011.

This is the second seafood processing plant of Huy Thuan Co and the fourth project to be constructed in Giao Long IP in 2011.

The new plant is built in an area of 1.7 hectares with designed capacity of 7,000 tonnes of products per year. The investment capital for this project was posted at 323 billion dong.

The plant is expected to be put into operation after 10 months of construction.

 