Fifth turbine in Son La hydropower plant ready to join national grid

25-Apr-2012 Intellasia | Kinh Te Vietnam & The Gioi page 3 | 11:23 AM Print This Post

Hoang Trong Nam, director of Son La Hydropower Joint Stock Co announced that after two months of rotor installation for the fifth turbine in Son La hydropower plant, the turbine was ready for starting idle run today, so as to officially join the national grid on April 30, 2012.

Together with the completion of fifth turbine, the company is also conducting the installation works for the sixth turbine at the same time.

Son La hydropower plant includes six turbines with total designed capacity of 2,400MW. Up to now, the first four turbines have been put into operation already, supplying 6.5 billion kWh to the national grid.

 