Vietnam to complete eastern section of north-south expressway project by 2021

19-Sep-2018 Intellasia | Hanoi Times | 6:00 AM Print This Post

The transport ministry has complete the feasible stuy of the project`s eastern section with length of 654 kilometers an investment capital of VN118.71 trillion (US$5.07 billion).

The Vietnamese Ministry of Transport (MoT) has set sight on starting construction of the eastern section in the central region of the north-south expressway in March 2020 an expects to complete it by 2021, accoring to the government portal.

The MoT complete the feasible stuy report of the eastern section of the project with length of 654 kilometers an investment capital of VN118.71 trillion (US$5.07 billion).

The project consists of 11 sub-components, incluing three public investment projects an eight projects uner the form of public-private partnership (PPP).

Of the PPP projects, the government is seeking opinions of ministries an agencies to etermine investment capital of three sub-components (sections Mai SonHighway 45, Highway 45Nghi Son an au GiayPhan Thiet), an uner the process of reviewing the propose investment capital of the remaining five (sections Nghi Sonien Chau, ien ChauBai Vot, Nha TrangCam Lam, Cam LamVinh Hao an Vinh HaoPhan Thiet).

Once the feasible stuy report is approve, the MoT will open competitive biing process to select consultants for technical esign an financial estimation, which is scheule to be complete in 11 months (from October 10, 2018 to August 2019).

Aitionally, the process of selecting contractors shoul take a total of 11 months (from October 2018 to March 2020).

Meanwhile, the MoT expecte the site clearance process to be complete by October 2020.

With regar to the three projects uner public investment, the MoT has complete the approval process for two sub-components, incluing the Cao BoMai Son an Cam LoLa Son sections, while the My Thuan 2 brige is in the final stage of approval.

It is expecte that the Cao BoMai Son an Cam LoLa Son section will be implemente in April 2019 an complete in 2021. The construction of My Thuan 2 brige will begin in October 2019 an complete by 2023.